Within 5 months, panic returned to Boubazar


 Within 5 months, panic returned to Boubazar. For the East-West Metro this time several houses on Madan Dutta Lane are cracked. This incident happened due to water entering the metro tunnel. On this day, it is seen inside the metro tunnel, the water is coming out at high speed through the wall of the tunnel. At a glance, it can be mistaken for a sudden waterfall. Metro engineers have started working on the grouting system to stop the flow of water coming out of the tunnel at high speed. Wartime operations are underway to stop the crack.


Crack panic returned to Boubazar again. This time, during the work of East West Metro, several houses in Gali Madan Dutt Lane next to Durga Pituri Lane have seen large cracks. Local residents noticed the crack early Friday morning. Due to this panic spread among the local residents. Local residents have expressed anger against the East West Metro Authority. They left the house in fear and came down the street with things. Residents have already vacated 10 houses. Police have been deployed in the area. Police personnel asked to vacate the cracked house. Metro representatives came to the spot, but they faced the anger of the residents.

The process of evacuating the residents of the affected houses to 5 hotels in central Kolkata has started. Special meters have been installed in affected houses so that any new cracks are detected by the meters. Local Trinamool MLA Naina Banerjee went to the spot. Ward No. 50 BJP Councilor Sajal Ghosh and CPM State Secretary Mohammad Saleem. Local Trinamool councilor Biswaroop Dey was on the streets since dawn.


Disconnect power:

Cracks have appeared in 3 houses on BB Ganguly Street opposite Madan Dutt Lane in Boubazar. Cracks were also seen in a printing press. There are not only cracks in the walls, but also in the floor. Electricity has been cut off in the affected houses.



Indemnity Assurance:

According to sources, KMRCL authorities have informed that the compensation will be paid within 15 days. A preliminary estimate by Metro engineers,

During the grouting work, water entered the tunnel and there was a problem. After four in the morning water started entering the tunnel. Because of that, the problem happened.

According to metro sources, water entered during the work of the cross passage.